We completed a refurbishment at Richard Hallam Primary; we refurbished four sets of boys and girls pupil toilets. We stripped out all of the exisiting toilet cubicles and sanitary ware. Our team of talented builders and craftsmen went on to create new door openings and plaster the area. We then laid new floor coverings, constructed new cubicles and installed new sanitary ware. After that, we carried out first- and second-fix electrical works. Lastly, we decorated the toilets and installed mirrors.
On completion of this project, we were honoured to receive some very special feedback from the pupils of Alderman Richard Hallam Primary School.
Contract Duration: Seven Weeks
Contract Completion: August 2015